SCR Surpasses Safety Targets with Kavach 4.0 and ABS Rollout

South Central Railway completes 487 Route Kms of Kavach 4.0 trials and commissions Automatic Block Signalling over 479 Route Kms in FY 2025–26.

Telangana

The South Central Railway (SCR) has recorded major progress in railway safety and capacity enhancement during 2025–26, surpassing targets in both Kavach 4.0 field trials and Automatic Block Signalling (ABS) commissioning. SCR completed Kavach 4.0 field trials over 487 Route Kilometres, exceeding the Railway Board target of 402 Route Kilometres.

 The trials were conducted in sections including Kazipet–Peddampet, Malkajgiri–Kamareddi, Charlapalli–Raghunathpalli, Guntakal–Raichur, and Mudkhed–Parbhani.

 The zone also commissioned Automatic Block Signalling over 479 Route Kilometres, surpassing the target of 357 Route Kilometres, in sections such as Kazipet–Balharshah, Vijayawada–Duvvada, and Wadi–Renigunta. SCR General Manager Sanjay Kumar Srivastava praised the Signal & Telecommunications teams and said both Kavach and ABS would continue to receive top priority in the current financial year.

Related Stories

Latest Articles

  1. Tamil Nadu CM Opposes NEP Three-Language Formula, Calls It Hindi Imposition
  2. The Lokarakshini Thalampulamma Temple festival is marked by a spiritual atmosphere.
  3. Staff directed to treat devotees with respect and a spirit of service.
  4. Free Laddu Prasadam Distributed to Devotees at Kanaka Durga Temple
  5. Railway Minister Inspects Sample Coach at New Delhi Station
  6. Hyderabad to Become India’s Sports Hub: Revanth Reddy Unveils Gachibowli Stadium Mega Plan
  7. "Sponsored Jungle Raj": PM Modi's Fierce Attack on TMC Over Malda Incident
  8. 📰 BREAKING: Trump Hints at Possible Breakthrough in US-Iran Talks
  9. BJP Confident of Forming Government in Tamil Nadu, Alleges DMK Corruption: Kova. Laxman
  10. Iran Internet Blackout Reaches Record Levels Amid Nationwide Digital Shutdown
Comments

Sign in with Google to comment.